CDOT workers remove old concrete on Monday.

Photo by George Kochaniec Jr. / The Rocky

CDOT workers remove old concrete on Monday.

Map my news

A daily update on the sinkhole at I-25 and 58th Ave.

* What was done Monday ?

Monday was a big day in the battle against "Sinkzilla." Not only was the exit to 58th Avenue reopened, but crews completed drainage, poured a concrete inlet, filled in the hole, compacted the area and prepared it for paving. Crews also completed removal of the old concrete and stockpile material.

* What will be done today?

Weather permitting, CDOT will begin concrete paving.

* When will all lanes open?

CDOT is still looking at 10 days

* Tip of the day:

Stacey Stegman, CDOT spokesperson, recommended car pooling, patience with delays or alternative routes.

Post your comment

Registration is required. Click here to create your free user account, or login below.

Comments are the sole responsibility of the person posting them. You agree not to post comments that are off topic, defamatory, obscene, abusive, threatening or an invasion of privacy. Violators may be banned. Click here for our full user agreement.




(Forgotten your password?)




News Tip

Know about something we should be reporting? Tell us about it.


Reprints